SDG&E has not filed its application.No filing in the CPUC Daily Calendar of November 10, 2026.What happens when it does

Meetings and deadlines

Share

Dated public meetings, plus the milestones everyone is waiting for. A milestone without a confirmed date stays off the subscribable calendar until it has one.

Coming up

  • November 15, 2026

    Save Fallbrook community meeting

    Fallbrook Public Utility District, 990 E. Mission Rd., Fallbrook. 2:00 PM.

    Source: Save Fallbrook

    Share this meeting

What to watch for

Expected, not scheduled. Each one starts a separate window, and missing one does not close the others.

  1. SDG&E files its application with the CPUC

    SDG&E told KPBS in September it would file by mid-November. The CPUC's project page, updated in October, says SDG&E has not filed yet and expects the filing by the end of 2026. The application gets a number and a public docket, and every formal deadline counts from it.

    Sources: KPBS; California Public Utilities Commission; SDG&E

  2. Protests, and becoming a party

    Under the CPUC's Rule 2.6, a protest is due within 30 days of the date the notice of the filing first appears in the Daily Calendar, unless the CPUC sets a different date. Filing a protest also makes you a party (Rule 1.4). Confirm the exact date with the CPUC Public Advisor once the filing is noticed.

    Sources: Rules of Practice and Procedure (Rule 1.4, becoming a party; Rule 2.6, protests); Methods for becoming a party to a proceeding

  3. Environmental scoping, 30 days

    The CPUC opens a 30-day scoping period for the environmental impact report, with scoping meetings. This is where route alternatives and impacts to study get put on the record.

    Source: California Public Utilities Commission

  4. Draft environmental impact report, at least 45 days

    Written comments on the draft report, the second formal chance to put evidence about routes and impacts on the record.

    Source: California Public Utilities Commission

Past meetings

  • November 9, 2026

    Town Hall: Fight the Powerlink

    Wilson Creek Winery, 35960 Rancho California Rd., Temecula. 6:00 PM to 8:00 PM.

    Source: Save Temecula

  • October 14, 2026

    SDG&E open house

    Borrego Springs Resort. 4:00 PM to 7:00 PM.

    Source: SDG&E

  • October 14, 2026

    Vista Irrigation District special board meeting on the Powerlink

    See the meeting packet. Time not published.

    Source: Vista Irrigation District

  • October 13, 2026

    Temecula City Council: Golden Pacific Powerlink update

    Temecula. Time not published.

    Source: City of Temecula

  • October 13, 2026

    SDG&E open house

    El Centro Community Center. 4:00 PM to 7:00 PM.

    Source: SDG&E

  • September 17, 2026

    CPUC public comment session

    San Marcos City Hall. Time not published.

    Source: KPBS

  • August 26, 2026

    SDG&E open house

    Embassy Suites, Temecula. 4:00 PM to 7:00 PM.

    Source: SDG&E

  • August 25, 2026

    SDG&E open house

    Fallbrook Community Center. 4:00 PM to 7:00 PM.

    Source: SDG&E

  • August 18, 2026

    San Diego County Board of Supervisors, Item 25: Golden Pacific Powerlink report

    San Diego. 9:00 AM.

    Sources: County of San Diego; OB Rag

  • July 31, 2026

    Save Temecula rally

    Duck Pond, Temecula. Time not published.

    Source: Patch

  • June 30, 2026

    CPUC webinar: Pathways to engaging with the CPUC

    Online (the recording is linked from the City of Temecula's page). Time not published.

    Source: City of Temecula

  • June 23, 2026

    Riverside County Board of Supervisors adopts a position of significant concern about the route

    Riverside. Time not published.

    Source: County of Riverside

  • May 14, 2026

    SDG&E virtual open house

    Online. Sessions at 12:00 pm and 5:30 pm.

    Source: Anza-Borrego Foundation

  • May 12, 2026

    SDG&E virtual open house

    Online. Sessions at 12:00 pm and 5:30 pm.

    Source: Anza-Borrego Foundation